STO in RBATP - Incorrect Requirement Date

Former Member
0 Kudos

Hello,

My scenario is that we use Stock Transfers using RBATP. I want to maintain a picking time of i.e. 2 days at the sending plant to prepare and process the shipment.  I use the transportation lane to determine the time between plants.  And I use the unloading time to cater for the time to putaway etc at receiving plant. 

  • Condition PICK has a 24 Hrs
  • Transportation time on Transportation lane has 72 Hours
  • Condition UNLD has 36 HRS

In the analysis of the Scheduling Results and log, everything appears to be correct.

this MAD is not transferred to the the schedule line in the sales order:

But the created STR is close:

How can I get the sales order schedule line to reflect picking time, transportation and unloading times?

Accepted Solutions (1)

Accepted Solutions (1)

babu_kilari4
Active Contributor
0 Kudos

Hello Lukas,

In your delivery proposal screen, you're highlighting the main item, but the confirmation was achieved from sub item ( see the yellow colored indicator where 47 CS of confirmation was achieved ). Can you click on the MBDAT of that line and see the confirmation picture. From what I look, it seems there are multiple schedule lines against that line. Can you post that screenshot ?

Thanks & Best Regards,


Babu Kilari

Answers (1)

Answers (1)

babu_kilari4
Active Contributor
0 Kudos

Hello Lukas,


There hasn't been any reply to the above comment made by me. Has the problem got solved ?

Thanks & Best Regards

Babu Kilari