CJA2 issue

amit_rajeshbhai
Participant
0 Kudos

Hi,

When i ran CJA2 transaction, i am getting double cost. I am wondering why this value category (OBRB) is coming and the cost is just double up.

Can anyone advice on this pls.

Thanks

Amit

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Amit,

Under CJA2 transaction code , Request you to run incoming order on WBS element level and not on project level.

only one element should be "Revenue element" for incoming order calculation.

Try & check .

Thanks.

amit_rajeshbhai
Participant
0 Kudos

I tried the way you suggested, but its giving the same result no change.

Thanks