on 06-29-2015 3:14 PM
Hello
My customer wants to create two mrp area (for sub contracting ) for 2 different plant for a vendor.
Kindly pour some ideas on this topic,
Venkat
This is not possible. Each MRP area should belong to one specific plant.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
You need to create two different MRP area assigned specific plants even though they have common vendor .
You can also carry out planning for components to be provided in subcontracting using an
MRP area by defining an MRP area for every subcontractor and assigning the components to be
provided to the MRP area of the subcontractor. You therefore plan the requirements to be
provided for these components for one subcontractor separately from all other requirements.
Depending on the requirements situation, the system creates either stock transfer reservations
from the plant to the stock of material provided of the subcontractor or it creates purchase
requisitions within subcontracting/third-party order processing, according to the special
procurement key settings.
Check the settings in SAP123 - Using MRP Areas
Regards
JH
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.