HI Experts,
We have uploaded the Grant Currency as USD instead of CAD.
We have even released budget, then when we took reports in local currency we realized that the currency is not right.
We have reversed the budget, changed the status back to initial draft.
Still the currency field is disabled.
Kindly help me on this, how to change the currency in Grant Master.
Regards
Omprakash
06-30-2015 6:31 PM
Dear Omparkash,
You can change the currency field to optional or ready for input in lifecyle field status of Grant Type, as shown in screenshot below:
Hope this resolve the issue.
Regards,
Amar Lal
07-01-2015 12:08 PM
Once budget posting has been done against Grant, it is no longer possible to change Grant currency.