on 06-29-2015 4:53 AM
Dear All,
I have an issue in Quality Info Record function. I have 3 vendors for the same material, 3 QIR were created for these.
- The first one, release until next year.
- The second one, release util date was exceed (on 3 days ago).
- The 3rd one, release until next year, but release quantity is exceed.
Default control key 0007 is set for the relevant material
Message mode = Warning is set for control key 0007 in SPRO
Block Procurement Order is set for all 3 QIR.
When I am attempting to create POs for vendor 2 and vendor 3, PO is created successfully with a warning message. (my expectation is PO block)
Then I try to reset Message mode of control key 0007 to Error in SPRO.
After that, I can't create PO for all 3 vendor. Error message "Procurement of material block for quality reason) (My expectation is PO can be created successfully for vendor 1 as this vendor's release date has not yet been exceed).
Please see attached screen shots for more details.
Can anyone help me with this?
Thank you very much.
Yongqi.
I went back and looked at your question closer.
The 0007 control key you mention only looks at the QIR (since you have "release required" on). If the QIR has something that blocks release of the PO, then by setting the error message to "E", it blocks all procurement activities including creation of PO. If it is "W" or "I" it allows creation of the PO. Most places want the PO's created and so set this to a "W". This is why when you changed the message type it prevent creation of the PO's.
Once th PO is created, the QIR record than determines if the PO can be released, NOT if it can be created.
In the QIR screen print you show an 03 block. Again, this only affect release of the PO, not creation of it. If you have this on, it should result in blocking the release of the PO regardless of all other values in the QIR. (This assumes you have your 03 set up right in configuration).
So when you ran it the first time around with the 0007 as a "W", it allowed creation of the PO's for all vendors since the QIR was there but the 03 block was on them. When you changed it to an "E" it saw the issues with the 03 block on them and prevented all procurement activities, including PO creation.
When you had it on as a warning, I would have expected all three vendors to have resulted in a warning message when the PO was created. Not just vendors 2 & 3. Maybe you also got it on vendor 1 btu didn't mention it since the PO was created and that's what you were expecting?
So I think the system is working as expected.
Craig
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Craig,
Thank you very much for your detailed explanation. I did receive a warning for all three vendors when creating PO. However, I can release PO and good receipt for all 3 vendors instead of only vendor 1. Is there any config I need to check? Or is there any rules for PO release that I need to take a look into?
Thanks a lot.
Yongqi.
I would double check that you are working with the right Q-info records. Are you by any chance using an MPN process and HERS materials in this process?
If the Q-info has a block on it, the order shouldn't be able to be released or if released, shouldn't be able to be GR'ed.
Make sure the block functions of the QIR are properly set in config.
Also, make sure you aren't looking at a vendor QIR and there isn't a lower level vendor/material QIR that is the one actually being used.
Craig
Hi, You mentioned that you have activated bloc purchase order option for all the 3 QIRs. Could you try removing block purchase order option for vendor 1?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
The block function is working independently from the Release date and quantity in QIR.
The block function will be set manually by the user and a reason should be manually maintained in QIR.
If release date or release quantity is reached, the system considers that the material can no longer be purchased from mentioned vendor and prevents the purchase order automatically from being created.
Hope this clarifies your issue.
Regards,
Ayoub.
What Ayoub is saying is that all three checks you are talking about are independent of each other.
If you put a 0007 block on the QIR it will block all purchases.
If the release date is reached, it will block all purchases.
If the release qty is exceeded, it will block all purchases.
The system is doing what you asked it to. The 0007 block is overriding everything else. It is usually used to manually block a vendor due to previous issues.
Craig
In the screen shots you provided it is reflecting that 0007 is set to Defect and not the warning. You should try again when the message mode is Defect. It should work. Below link explains the functionality.
Release Criteria for Procurement Functions - QM in Procurement (QM-PT-RP-PRC) - SAP Library
Anand