on 06-26-2015 7:36 AM
Hi SAP Experts
Can anyone explain me whats Dynamic Cut Off Scenarios in GATP Scheduling
Has anyone come across some scenarios or this functionality
Regards
Harsh
Hello Harsh,
The statment is quite generic. Can you explain us the business scenario that you're trying to achieve in Scheduling ?
Babu Kilari
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Babu
Thanks for your query:
The Details are as described below:
Business Scenario:
To pull in existing order cut off time from 3pm to 11 am for the ship to party.
This enable dynamic cut off.
Problem statement:
In practice, there are different cut off time for each ship to parties.
But today we have ONLY ONE setting in SAP for order cutoffs per plant.
So, we need to manage other cutoffs manually outside SAP.
Usually they are set at the earliest possible time creating buffers in the system and causing RDD:CDD mis-matches
Sometimes the setting is at the latest possible time causing CDD & RDD misses & capacity issues
Regards
Harsh
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.