on 06-25-2015 4:55 PM
Hello There ,
I was using the status and release management for the document status network .
The issue when I configure 5-6 status , the graph does not shows in the correct sequence . My previous status and next status are all messed up .
Do you know how to fix this issue . It seems to be a waste feature if status network is not shown properly .
Advices please !!
Regards ,
Abhishek
Hi,
thee graph is unfortunately only depicting status in ALPHABETICAL order. So first of all a complex status network can not be represented, and for a unidirectional status network I recommend to use status like 1-Draft, 2-For Review, 3-Approved, 4-Released, or similar.
Ulf.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ulf ,
We have also same problem..
May be for simple Status schema , your recommendation is good.
When Status schemas has be shown in other languages for example German , this recommendation may not work.
Can we expect any correction note or Improvement Note from SAP ?
Thanking you ,
Regards,
Satya
Hi Abhishek,
The status network is not for displaying Graph, because of simple reason status can be parallel and that can not be configured in webdynpro Ui element. ( at least when it was getting developed at Ehp6 ).
If you want to know next status and previous status of current status then there is an option call " Explore status schema " they will show you next and previous status .
Hi Ulf,
Any object can have multiple parallel status, so it was not possible at WD ABAP to show as parallel status, hence we have option called " Explore status schema " which w
Regards,
Varun