on 06-24-2015 8:11 AM
If you will look at overall flow of the Production staging / Consumption then
Prod Order Creation----Release the PO ---- Run Material Staging (System creates TR) ---Convert TR to TO (Destination bin in the TO is based on the Control cycle)----Confirm the TO at line side-----Perform FG Goods Receipt / Consumption (FG will get posted as + and component will get reduced from the bin which is there in the control cycle if control cycle record does't exist then system will pick the storage type detail from movement type (261) and a negative entry will get stamped in storage type 914 with production order as Bin number) you need to manually transfer the stock from physical storage type to storage type 914 using t code LT01 to make it zero
in your case you are performing CO27 which will post the FG goods receipt and at the same time consume the component stock from the bin specified in the control cycle. Could you please check whether control cycle is maintained for the material or not
For process flow please have a look on the below mentioned thread http://scn.sap.com/thread/3663170
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
if no control cycle is maintained then during CO27 system will consume the stock from the 914 storage type(in standard SAP "Allow negative stock" is activated at storage type level) and later on you are supposed to use LT01 transaction to move the stock from physical bin to 914 storage type to adjust the negative quant.
Hi Eric
I just checked your scenario , what I observed after creation of production order , if I am not wrong you are doing CO27 - picking list , & system generate material document , you can see there your TR .
but 1st let us know , which staging strategy you are using .
because material will come first to supply area 7 then staging area to shop floor .
because when you confirm the production order system also generate one material document & one TR
when ever you create the TO , system will pick the material from staging - 100 storage type bin- dynamic bin (production order number) to 914 storage type & dynamic bin (same production order number) & after TO confirm system will issue the material to shop floor .
Check the stock overview LS24
check your storage type strategy & movement type table properly for auto TO , I ,
think it will help you
Regards
Dillesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Eric,
Have you solved this problem?
Regards,
Steve
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
sorry all, let me correct typo, it's for 261 Mvt, 914 is the storage type.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You need to activate the automatic TO creation for WM movement type :
SPRO + logistics execution + warehouse management + interfaces + inventory management + define movement type + LE-WM Interface to inventory management.
Find your reference movement type and put an X in column for immediate TO creation.
Rgds,
Philippe
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please go through the FAQ note 566090 - FAQ for immediate transfer order creation
and the troubleshooting in 87194 - Direct transfer order generation
Hi Eric,
Can you see the transfer requirement in LB10 and create the TO manually ? May be you have an issue with the TO creation (removal strategy, ...).
With an X instead of a A in immediate TO creation, you can also check with LT06 that the TO can be created correctly for your MM document.
Philippe
Hi Eric,
The TR is always automatically created and you can see it in transaction LB10. From there you can create the TO manually from the TR. That's what I would like you to try now, in order to check that the TO can be created manually without problem. I know you want it to be created automatically but we need to check first if it goes well manually.
The second option I was proposing to you, instead of the check with LB10, was to try to create the TO, also manually, with transaction LT06. In this transaction you need to enter the material document you posted. It is an alternative if you have problems to find the right TR in transaction LB10.
Rgds,
Philippe
wonders me.
It is for example said that you should have customized mail as it is the ONLY way to know why the TO could not be created. Do you have this done, what does the mail say?
Also saying " I can't create the TO for the material document" does not really tell much, do you get an error message? Which one? this would be something that could help to get you further.
Always remember we can't access your system, we do not see what you do, so you have to provide the information to let us know.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.