There is one Scenario , we producing some sheet metal component in-house, due to capacity overload we r sending ROH for job work (subcon) also,
so my quire is what r the views to be maintain in material master to capture in single material code.
regards,
Bharath
Hi Bharat,
In addition to rohit's reply maintain procurement type as X in MRP 2 view and When MRP is carried out system will generate Planned order for this..Now based on the scenario (in house production or external ) you can convert to production order or purchase requisition...
Hope this helps...
Thanks
Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
Here you are sending the ROH material to do the same job as like you in house .So when ever you will create Production Order with an external operation subcontracting option in Routing , it will generate the PR in the same Production Order -Operation view -External Processing Tab .
To achieve the Sub-contracting you need to do the following setup as per this doc
http://scn.sap.com/docs/DOC-49346
Hope it helps .
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Bharath,
You need to have Basic view, MRP & Purchasing, Costing and Accouting views atleast.
If you have WM and QM management activated and those views need to be maintained. It is more related to what all business processes you want to carry out for this material.
Regards,
Rohit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
86 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.