No HUs have been transferred for material

0 Kudos

Need help with the following issue :Packing in VL02n

TO was confirmed and then on the time of PGI. Handling unit was deleted without performing "unpack". Now unable to repack it to perform PGI, probably because the HU which was created while TO confirmation is deleted and also the material in lower "materials to be packed" window is greyed out. i cannot select it.How can i repack and perform PGI ? i have to use the same delivery number, cannot recreate it.

Accepted Solutions (0)

Answers (1)

Answers (1)

claire_yang
Contributor
0 Kudos


Hi, 

Have you tried to adjust the delivery quantities based on the packed quantities, then pack it again? For further help please consult experts in LO-HU area. Most of them are in ERP space, not SCM.