MRP not considering PDT while proposing PR in MD04

Hi SAP Gurus,

MRP is not considering or taking Planned delivery time while proposing Purchase requisition for Independent requirements. The PR's release date, planned date and delivery date are all same. We have maintained PDT as 14 days in Material Master (it is external procurement).

In Purchase info record also for the vendor , PDT is maintained as 14 Days.

In OMDT also for Plant / MRP group , it is defined.

I have attached screen shot of MD04, MM03, Info record and OMDT settings.

Please give your valuable inputs on why MRP is not taking PDT while proposing Purchase requisition's ?

Thanks In advance. Pl provide your valuable inputs, it is urgent.

Best Regards,

R.Velmurugan.

MM03.PNG (49819 B)
MD04.PNG (54236 B)
replied

Hi Velmurugan,

PDT maintaned at scheduling agreement has higher priority then info record. In your case, system is considering PDT from sch agreement.

Regards,

Rohit