on 06-18-2015 3:38 PM
Hello,
Here is a strange issue that we are having. In PO line item (in ECC) the schedule lines are like below
Schedule line ID Quantity
1 100
2 200
3 300
It goes to SNC and user opens this PO.. all looks ok. After clicking on change , Confirm (PO item) , Save and then Publish. The data reflected on ECC is in reversed order. But the confirmation tab has the same old sequence.
Schedule line ID Quantity
1 300
2 200
3 100
Has anybody seen this issue? Any suggessions?
PS: There are no user exits or BADIs for any custom logic for processing all the interfaces between ECC - SNC.
Thanks,
Amit.
Hi Amit,
Could you check change log for these line item(s), i.e. who made the change (in ME23n)?
Regards
Rahul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.