How to post goods issue to production order using ProMan.

Production order is created for making inhouse assembly. Assembly material BOM contents Raw material . This Raw material is procured and in CNMM (ProMan) it is appearing in Project stock.

However when material is being issued to production order/reservation,  the "Post goods issue (field)" appears in gray color. Hence not able to Post goods issue to production order.

Would like to know the process of goods issue in ProMan.

Thanks & regards

Vikram

Accepted Solutions (0)

Answers (1)

Answers (1)

sunil_yadav2
Active Contributor
0 Kudos

HI Vikram,

i dont see any settings related to field selection for PROMAN. this might be Authorization issue Please check SU53 screen when you get gray field for PGI.

in SAP Standard below are the steps:

Posting a Goods Issue

You use this function to post a goods issue for a reservation, for example, for production. This is for internal procurement only and the item category must indicate inventory management. You cannot post a goods issue for a delivery here.

  1. Select the component.
  2. Choose Execute.
  3. Choose Post Goods Issue.
  4. Enter the required data on the dialog box that appears, such as the quantity for which you want to post the goods issue.
  5. Choose Execute

The change is shown on the Quantities and Stock overviews.

thanks