on 06-18-2015 4:37 AM
I have two questions.
The LOP Manual only indicates that the background program should be running continuously. I have the job frequency set to 10 minutes. I wasn't sure what was appropriate.
Cheers,
Dan Mead
Hi Dan,
unfortenally the LOP program in Solution Manager (we have SP12) is not as good, as it could be.
Definitly: you schedule the job only once and the abap report is running infinitely. For my that is broken by design, because it occupies one background workprocess the whole time.
Kind regards,
Christoph
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.