on 06-18-2015 5:38 AM
Dear Sir :
FG Material Number : R-F110
Strategy Group : 10
PIR : 100 + 200 + 300
Collective Req. Indicator : Set
After MD02, the planned order in MD04 should show a cummulative qty for 600 nos, since Collective Req. Indicator is Set.
But actually seen is three planned order as 100 nos + 200 nos + 300 nos.
Why ?????????????
Thanks in Advance,
Dinesh Kumar V.
Hello Dinesh,
Individual and collective indicator work in make to order to have the collective requirements for sales orders. In your case strategy is 10 which is make to stock.
If you want to collective requirement for your material use the period lot size like MB
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
9 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.