on 06-16-2015 1:59 PM
Hi,
I have four questions with regards to serial number setup and would appreciate your help.
Background: running in a SAP WM environment.
Scenario A:
We are required to input serial number during putaway in the warehouse, and further, we are also require to input serial number during goods issue dispatch out from the warehouse.
Question 1 for scenario A:
Does the following serial procedure setup fits the requirement?
MMSL 03 (serial usage) - compulsory
SDLS 03 (serial usage) – compulsory
Scenario B:
We are NOT required to input serial number during putaway in the warehouse, but it is an optional to enter serial number during goods issue dispatch out from warehouse.
Question 2 for scenario B:
Does the following serial procedure setup fits the requirement? What if a serial number is entered during outbound delivery, and may I know if this will become an issue during Goods Issue
MMSL 01 (serial usage) – Not require (none)
SDLS 02 (serial usage) – optional
Question 3:
The MMSL is a serial procedure used for goods receipt and goods issue. May I know what serial procedure is used for stock transfer and stock count?
Question 4:
The MMSL is a serial procedure used for goods receipt and goods issue, and the SDLS is used for outbound delivery. That means the following setup will be a conflict because if a serial is entered during outbound delivery, system will trigger error during PGI?
MMSL 01 (serial usage) – Not require (none)
SDLS 03 (serial usage) – compulsory
Regards,
Tuff
First Thing - First SAP WM does not support serial number. Only way you can track them using batch management for such materials or storage unit management.
Serail Number possible to enter time to delivery and goods movements. Serial number entered in the Delivery will flow to your material document of PGI or PGR.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Serial number in Goods Movements- MMSL is the procedure that you need to use.
For Deliveries you have to SDLS. I am not sure but I do not think MMSL and SDLS will conflict as serial numbers will flow from delivery documents to MM documents..
Note- PGI happen in the background for deliveries so I do not think it will have any impact