on 06-16-2015 2:18 AM
HI
Facing an issue while running the transaction RE_RHGRENZ4 to delimit the qualification as this is a standard program, so there is no changed which had happened.
Has authorisation to execute. But still after executing the transaction, system says test mode on , chossen end date not possible.
As this is only information after pressing enter, it shows the data has been changed but when actually checked in the qualification with the overview nothing has been changed.
File is attach for refrence. Kindly sugest.
Thanks
Sanyam Bhatnagar
Hi,
Kindly share the screen shot of your Issue.
Regards,
Venkat Polisetty.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Venkat
I am unale to put th screen shot in this and not able to attach, can you send ma a test mail on sanyam.bhatnagar@in.fujitsu.com, so I can send you the details
Hi,
Please run RHGRENZ4 report with the following parameters:
OBTYPE: Q
OBJID: Qualification ID(Eight Digit)
New End date 02.06.2015
Infotype: Blank
Subtype: Blank
Existing end date 31.12.9999
If still you will not be able to do this try below solution also:
In the IT0024 - screen, change the preview period to the period as of which the qualification isn't applicable anymore for the employee and delete the specific qualification.
What SAP does as this moment is delete the qualification only for the preview period. If you change the preview period again from (let's say) 01-01-1900 you will see the delimited qualification.
Example
Regards,
Venkat Polisetty.
Hi Venkat
I have tried the below options multiple time
1. RHGRENZ4 report with the following parameters:
OBTYPE: Q
OBJID: Qualification ID(Eight Digit)
New End date 02.06.2015
Infotype: Blank
Subtype: Blank
Existing end date 31.12.9999
2.
OBTYPE: Q
OBJID: Qualification ID(Eight Digit)
New End date 02.06.2015
Infotype: 1000
Subtype: A032
Existing end date 31.12.9999
3.
OBTYPE: Q
OBJID: Qualification ID(Eight Digit)
New End date 02.06.2015
Infotype: 1001
Subtype: Blank
Existing end date 31.12.9999
4. Even with the evaluation path as well but still the same.
We have 2000 qualification which needs to be delimited.
That is the reason I was trying to do it from RE_RHGRENZ4 to do it in mass.
Thanks
Sanyam Bhatnagar
Hi,
Try below solution for the same:
In the IT0024 - screen, change the preview period to the period as of which the qualification isn't applicable anymore for the employee and delete the specific qualification.
What SAP does as this moment is delete the qualification only for the preview period. If you change the preview period again from (let's say) 01-01-1900 you will see the delimited qualification.
Example
Regards,
Venkat Polisetty.
Dear Venkat
Received the below reply from SAP
Dear customer,
Could you please implement the newest version of RHGRENZ4 report
available from note 1642614 and 2136774? This report was completely
rewritten and the functionality has been slightly changed. The report
has a new documentation as well and the note has a document with
examples that show how the report is supposed to deal with certain
datasets.
Sorry for the inconvenience.
Let me implement this and update.
Thanks
Sanyam
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.