on 06-15-2015 10:46 AM
Hi,
I am a novice in SAP TM and need experts guidance in this query,
Loading and the Unloading date of FU is having the past date of the acceptable start date for some of the FU.
I agree the pick up and devliery date will be taken from the DTR document to the FU. Based on the dates in the DTR, the acceptable and requested start and end date will be calculated.
But here, I would like to know how the Loading and Unloading date are populated in the FU document and further flow to the departure and arrival date to the FOR.
Because of this inconsistency in few shipment , planned ship date becomes the shipment start date and hence becomes incorrect as per the customer schedule.
Thanks for your much help.
Regards,
Premalatha. S
Did you figure this one out?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Can you please compare these dates with the dates of Freight Order/Freight booking associated with this FU?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.