Hi Team,

i need the below result when running rescheduling,

When running rescheduling  and if there are two orders  and one is with requ. date next month but creation date is yesterday

Another sales order which created today but req. date this month am expecting that reservation should be for the order with requ. date this month though it created later on.

How to achieve this?

Thanks to help.

Accepted Solutions (0)

Answers (2)

Answers (2)

0 Kudos

Hi,

on the initial screen of TC V_V2 you can influence the sorting of the documents.
Regarding the date you will find two options there:

1. Sort item by date of creation

2. Sort by delivery date of earliest schedule line

The second one should correspond to your needs.

Please also consider the priorities of the sorting criteria.

Best regards,

w.