on 06-12-2015 6:01 PM
Hi ,
I am trying to do data loads from HR system (Time Management extractors 0HR_PT_1,2,3) to BW production systems, but i am in confusion whether do i need to take down time for the data loads or not required. Does any one have experience on this? Thanks in advance
regards
Manoj
Hi Manoj,
To load data from one system to other you dont need a down time.
Best Regards,
Shivanagouda Ningodti