Dear SolMan experts.
When you document transactions, customizing objects and development objects in project systems via SOLAR business process structure in implementation/upgrade projects - what do you do with them after go-live?
Suppose that they were in documented when Solman was connected to the project systems via LOGON/TRUSTED RFC's.
Do you just change the systems in corresponding logical components to match your maintenance transport route and use the documented objects for maintenance, break-fix and support development and transports? What are some of the common practices?
For this you have logical components with an assigment of technical systems in transaction: SOLAR_PROJECT_ADMIN. There you can maintain, what are development, test and productive system.
If you finish your project, your solar-project can be used to create a solman "solution", which is designed to handle productive projectes later. I a solution you will find same project structure and business content as in the project.
Kind regards,
Christoph
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Great answers everyone, thank you.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Viacheslav,
The implementation lifecycle using Solution Manager is:
1 - Define your system landscape (development, quality, production systems)
2 - Associate your system landscape to a Logical Component (e.g. for ERP) which comprises all environment rules you set in your system landscape
3 - Define which business scenarios/processes/process steps you will use
4 - Configure the system to enable the business processes
5 - Test/Approve the configurations made
6 - Promote your projects to production. At this point, you will close your implementation project and transfer your business process tree/documentation to a "solution" which is used to monitor how your business process are being performed productively and over time you may encounter some points that require adjustments/enhancements
7 - Create maintenance projects with the branch of business process that need to be change and go back to tem 4 ( items 4-7 will represent your continuous improvement).
Regards
Valdecir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
11 | |
10 | |
9 | |
8 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.