Hi,

maintained OT in 2011 & running the time evaluation in TO20 overtime it is updating..

I have to pass the this to payroll.. to get the amount ..

Please help!!!

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member182377
Active Contributor
0 Kudos

Hi Srinivas.

Is your question answered.. if yes mark the correct and helpful answers and close the thread.

Thanks

Sriram

jagan_gunja
Active Contributor
0 Kudos

Time w/t's are valued with basis w/t's like /001, /002.

Check the val.class in table/view V_512W_B for the relevant w/t's

Run payroll with log (simulation will do).

Check the RT at the end.

If the amt is not correct for your w/t, then go through the log for sub schema XT00 where time w/t's are valued.  Check  whether val.basis is correct. The check how the value is calculated.

former_member182377
Active Contributor
0 Kudos

Hi

Can you see the value in ZL table in time evaulation.. Because ZL table is the bridge between Time and Payroll..

once you can see the Overtime Values in ZL table.. run payroll and check the schema TC00 whether it reads the value from ZL table

Thanks

Sriram