on 06-11-2015 12:27 PM
Hi All,
I am working on a Classic scenario wherein we create a contract in the ECC and the contract should be used while creating the sc
I would like to know the standard configuration for the SC to access the contract in the SAP ECC through RFC connection
Thanks in advance
thanks
Sreenivasa chary
Hi Sreenivasa,
Could you please check with your technical team on this method - SOS_VALIDATE in the class /SAPSRM/CL_PDO_BO_SC.
This might give some useful info since I am not sure on what exactly your requirement is.
Best Regards,
Bharathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Bharathi,
We use the classic scenario,
the contract is created in ECC system in ME31k (contract is not replicated to the SRM system)
when we are creating the SC, and providing the Product number/plant/vendor same as in the contract,
the SRM system should identify presence of contract in the MM system (we have a validation that without contract we cannot create the SC)
so now we want to know how can we create such a scenario could you kindly guide me in this regard
thanks
Sreenivasa chary
Hi,
have you uploaded the contracts ECC to SRM ?,bbp_contract_initial upload!
Regards,
kiran
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
helloo ajith,
contract details are fetched from EKKO table
fetch all the PO's raised against the contract from EKPO table
and then you have look for remaining quantity or price depending on the type of the contract
export the values to SRM, in srm you have RFC program which would import the the values and then use them according to the requirement of the client
thanks
Sreenivas chary
hello all,
Issue is resolved ,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
SRM should propose to the requester the possible source of supply available for the cart. Depending on security the requester can assign the source of supply (assign the contract to the cart) based on the vendor , part, plant (as per contract info). Regards, Daniel