on 06-11-2015 7:08 AM
Hi Everyone
contract date 19.04.2011 to 18.03.2014 cash flow from 19.04.2011
Then change the date to 01.04.2011 to 18.03.2014 cash flow from 01.04.2011
check the table “vicncn” the cash flow start date didn't update~it still 19.04.2011
but I can change the cash flow start date after the 19.04.2011
How can I make the contract start date and cash flow statr date is consistent?
Hi,
Please execute transaction RECDCGOL and forcibly regenerate the cashflow.
Regards,
Sid