Hi PP experts,

I want to execute MD50. I have maintained the following data.

I get the mrp result as,

Then when I do MD04,

then I am not getting the planned order to convert them into production order.

What configurations are required in SPRO for MD50.

Please help me out.

Regards,

Sagar

Former Member
Former Member replied

Yes. Rupesh,

The sales order is fully delivered.

Therefore the problem was occurring.

The SD person completed the whole SD cycle up to delivery.

The sales order is completed.

That's why the problem was there.

Thanks everyone for your valuable response and time as the discussion was too long.