cost component splitting

Former Member
0 Kudos

hi friends

In oktz we will create the cost component structure and figure for each cost component can see in ck51n.  plz help me out  where we can see single cost component splitting figure ( amounts ) for particular product for example:-  we assume 2000 is a product.  manufacturing of 2000 we should required  cost components like raw material, labor,  machine etc in that each cost component(machine) will include of so many activities. if there is chance to see that splinted  activities figures amount

Accepted Solutions (0)

Answers (1)

Answers (1)

pavan_kumar18
Active Contributor
0 Kudos

Hi,

using OKTZ we can define the break up of cost component structure.

Here we can decide the number of components required for a material depends on your company's requirement.

This is totally configuration Area.

To see the breakup of cost component for a material, 1st you need to estimate the material using the T code: CK11N

Then you need to mark and release the cost estimate using the T code: CK24

You will get cost components for a material using the T code: CK13N.

Regards,

Pavan Kumar Arvapally