I have a requirement where I have to extend RFx simultaneous opening process in SRM system.

I tried implementing Badi (/SAPPSSRM/BD_SIM_LOGIN) but unfortunately it is not getting triggered.

Please let me know if I am missing some thing.

Regards,

Abhinav

Accepted Solutions (0)

Answers (1)

Answers (1)

vinita_kasliwal
Active Contributor
0 Kudos

Hi Abhinav

Did you ensure all the per-requisites are met ?

Also SAP has provided a config node by which we could activate the functionality so I am not sure if you are doing the right thing ..

Can you try that as well ?

Prerequistes: SRM_SOURCING_1 must be activated.

CONFIG:

SRM Server  RFx  Extended RFx Process  Simultaneous Logon  Activate/Deactivate Simultaneous Logon at RFx Response Opening

Refer links for more details

SRM, Strategic Sourcing Innovations - Business Functions and Customizing Switches - SAP Library

Simultaneous Logon at RFx Response Opening - Sourcing and Tendering in the Public Sector - SAP Libra...

Extended RFx Processing - Strategic Sourcing with RFx - SAP Library

Regards

Vinita

Former Member
0 Kudos

Hi Vinita,

Thanks for your reply !!

As per SAP standard, simultaneous logon functionality is activated to enable the approvers
to approve the opening process simultaneously within a specified duration.

Duration of the simultaneous logon is configurable, meaning RFQ response openers must logon to
the system and approve the process within the configured period. If they do not
logon within this period, the simultaneous logon process fails and the
purchaser should re-initiate the logon process.

Also as part of SAP standard, if the RFX response openers have approved the opening process the
system still waits until the duration of simultaneous log has expired to complete the process.

A development is required to automatically extend the simultaneous logon process if the
approvers have not yet approved the opening process and to successfully
complete the process once the approvers have approved the opening process.