Hello together,

i know that it is possible to implement a Milestone Tab in cProjects, where you can grafically see all Milestones of the Tasks.

How can I do this?

Thank you!

Accepted Solutions (0)

Answers (1)

Answers (1)

judith_gabriel
Contributor
0 Kudos

Dear Rüya,

the following switch must be activated:

Area: '0002' - Master Switch

Name: '0013' - Milestone Trend Analysis

settings = 'X'

Afterwards, you can activate the milestone trend analysis for relevant project

types in project type Customizing. (See SAP Note 1759150.)

Best regards,