Deletion of old planned independent requirements

Hi,

I have a question, when the stock of material doesn't cover the PIRs, we require delete it until the material purchased arrives. The available stock is 50 units and i have 2 PIRs, exactly 50 units per week, as you see, the end PIR won't be satisfied. If the supplier's leadtime is 2 weeks and the objective inventory is 70 units. When I run MRP, i get a SOLPED by 120 units, but because of 50 units that it won't supply, the SOLPED must be by 70 units. Actually the 25% of materials have this problem because of a market situation. We configured compensation mode and horizon adjustment but it doesn't result, we need analize first and then use MD74, MD75 to delete PIRs

Thanks and regards

Karin