Hi Gurus.
We faced the problem while creating FI documents (FB50) postet to WBS element (company code B), when it's existing in project with assigned company code A. We've got an error KI100 saying "The CO account assignment object belongs to company code A, not B". ge
Already turned off this messege, but no use. Company code on project level is obligatory on system level.
Is there any solution to ake postings on WBS with different comapny codes under one project, without deviding project in two separate?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Paulo, Thank you so much. The problem solved...
I was trying to change Requesting Company Code for wbs and it didn't help.
The thing was that screen 1410 was hiden and didn't show up. After defining own view of the detail screens, I finally can change Company code. And under this conditions everything is fine.
Hi
Check if the following note may be helpful for you.
998849 - KI100 with account assignment to WBS element
Regards,
Sudhakar*
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Privet Kir,
Within same CO area it should not be a problem. Also Company Code is not a mandatory field on the project definition unless it is made mandatory in customizing.
Regards,
Pav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Privet,
The problem is that cross company posting isn't configured. And FI department says that that's not suitable for their configuration.
With Company Code on project defenition i tried many varieties. When creating Project it asks for CO or CC or Plant, When i fill one of those fills it asks for CC anyway. How can i leave it blank? May be some ticks in OPSA? No obligatory customizings for fiels has been made.
Actually there should be no problem even if you have the default Company code at the project definition level too, as soon as your particular WBS is assigned to another Company code.
Maybe your problem (as mentioned by Pardhu) is just because your Company code is defaulted when you are trying to post FI GL document? So, you need to switch to another Company code and next try to post for that Company code.
So the message is not related to the Company code on the project definition, but to the fact the system has that Company code in the document header for FI GL posting that was defaulted either from a parameter or from previous postings.
I usually change CC in FI GL document posting to the same that written on WBS . This is what results errors.
If I post FI/GL with CC 'A' to WBS 'A' (Project Definition 'B') = Error KI100
if I post FI/GL with CC 'B' to WBS 'A' (Project Definition 'B') = Everythings fine because CC 'A' matches what's written on Project defenition... And all WBS in this project has this CC defualt by system, no matter what value i enter in Requesting Company Code for wbs.
Now it's also a problem to Create Purchase order with the similar error.
Dear,
Is your controlling area is common fro all company codes?
Reagrds,
Pardhu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
In FB50 we need to post with respect to single company code.If you have multiple company codes, you need to change company code whenever posting for different company code.
in FB50 out put screen -->Edit-->Change company code or press F7 on FB50 out put screen.
Kindly try with this.
Regards,
Pardhu
Hi Kir,
Is the cross company postings allowed by your FI department?
Ideally you should be having a structure for Company code A and different structure for Company code B within the same project.. And you should be posting to same company codes using FB50.
WBS A for CC A and WBS B for CCB in you project..
You shouldn't post to CC B using WBS A and vice versa..
Hope it helps...
Sammar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for reply,
Can you please explain what do you mean by "different structures within the same project." Now I have two 2-nd level WBS elements, under common WBS element 1-st level, Several WBS 1-st level elements are forbidden in our configuration.
That what i do, Trying to post CC B to WBS (CC B) - Shows error regarding that Project has CC A.