PI Upgrade from 7.30 to 7.40 - Wizard Necessary?

former_member229542
Active Participant
0 Kudos

Hi Guys,

Its required to execute a PI Upgrade Wizard after upgrading from 7.30 to 7.40?

Im aware that upgrading from previous versions it was required as mentioned in Note 1321868 - Configuration Wizard: PI Upgrade but it seems to not apply in this Upgrade Sceneario

Any experience advice would be highly appreciated.

Best

Martin

Accepted Solutions (1)

Accepted Solutions (1)

hemanth2
Product and Topic Expert
Product and Topic Expert
0 Kudos

Dear Martin,

Hope you are doing good.

Nice to hear from you again.

You do not need this, just see note 1444305 - Configuration Wizard: PI / ESR Support Package Update along with the readiness check as per note 817920 .

  

Hope this helps.

_ _ _ _ _ _ _ _ _

Kind Regards,

Hemanth
SAP AGS
_ _ _ _ _ _ _ _ _

former_member229542
Active Participant
0 Kudos

Thanks!

Answers (0)