cancel
Showing results for 
Search instead for 
Did you mean: 

AVAC Activation at Activty Level

former_member282774
Participant
0 Kudos

Hi Experts,

I have activated AVAC with Tolerence Limit and group are ++ and 80%(Warning),90%(Email to Per Resp) and 110%( Error Message).

But It  appears that AVAC  controls the spending at the Activity level  instead at the WBS level.


Though we have enough budget at WBS element level(High Level),when user is trying to create a PO and assigning Network and Activty it giving an Error message saying that Budget Exhausted.


IS this a standard behavior? Please advise.

Accepted Solutions (0)

Answers (3)

Answers (3)

MTerence
Active Contributor
0 Kudos

Hi Srini,

Do you have Budget at WBS element, still you get Budget exhausted message when you assign cost to Activities.

Regards

Terence

former_member282774
Participant
0 Kudos

Yes,AVAC activates when we REL the Budget.

@ Maria:Yes ,we have enough budget at WBS element(We only have one Hig level WBS) but System restrciting when we try to create Commitments using Network as an Account Assignemnt Object.

Is this a standard behavior?

MTerence
Active Contributor
0 Kudos

Hi Srini,

Do check reports, whether the Budget is consumed in terms of Commitments planned.

Actual Budget is checked against Actual and Commitments planned. This does not look like standard behaviour. If there is budget in WBS element, system will allow you to plan cost under network activities.

Also you need to consider whether the Budget check configuration is made Total or Annual or release etc.

Regards

Terence

former_member210342
Participant
0 Kudos

Hi Srini,

This is standard behavior, WBS is CO- Object, So whatever commitment you post against Network/Activities will consume budget from WBS.

As you said, you have one higher level WBS , So check whether budget is assigned to Lower level WBS against which you are posting Commitment.

Or If you have not distributed budget to lower level WBS, It  means you are consuming budget from higher level WBS. So Check how much available budget is there.

Please share the Screenshot of Cj33 and S_alr_87013558.

So that we can analyse the case

Hope it will Help

Thanks

rahul

former_member210342
Participant
0 Kudos


Hi Srini,

I agree wid Pradha,

Network acitvity use budget of its respective WBS.

If you r creating PO with respect to Network/Acitvity. then it wil utilize the budget of WBS on which it is assigned.

Your setting states that Error message at 110% means watever budget is assigned ..it is fully utilized.

How ever if Budget is visible as available . Please check it is also released.

Check settings OPS9 wheather Avac control is activating on Release or overall.

If it is on release then Whatever budget is assigned might be it is not fully released.

I hope it will help

Rahul

pardhreddyc
Active Contributor
0 Kudos

Dear,

It is standard behavior only.You assigned network to WBS element for which budget was assigned.

Kindly check SAP help on the availability control.

Principle of Availability Control

Activating Availability Control - Internal Orders (CO-OM-OPA) - SAP Library

Regards,

Pardhu