Budget Exceeded error after Settlement RUN.

Former Member
0 Kudos

Dear Expert’s,

I faced the problem while click on saving/check the release budget in CJ32. Basically it’s happened after run the PS settlement. (During the settlement run I face problem “Budget exceeded” and then I run Budget deactivated by CJBW then settlement run perfectly.) I thing/ perhaps here have mistaken in configuration. Please all GURU/Experts make helping hug to resolve this issue as soon as possible. 

In bellow I shear my configuration on Settlement Profile, Network Settlement Profile, network Profile, Planning Profile, Budget Profile, Availability control and project profile.


1. Problem

2. Settlement Profile

Project Profile Planning Board Tab

Project Profile Controlling Tab:

3. Settlement Profile

4. Network Settlement Profile

5. Planning Profile

6. Budget Profile

7. Project Availability control (Tolerance Limit)

Accepted Solutions (1)

Accepted Solutions (1)

MTerence
Active Contributor
0 Kudos

Hi Hamayet,

Refer this thread, whether this is helpful

Regards

Terence

Answers (3)

Answers (3)

ved_prakash2
Discoverer
0 Kudos

Hi Folk,

Could you please help me to get this note:
1935079 - Error message BP604 budget exceeded during settlement

It seems SAP has been removed it & facing the same issue at the time of CJ88.

Former Member
0 Kudos

Dear All.

My Problem Have been successfully solved.

Thanks for all of your support.

Regards

Hamayet Rasel

MTerence
Active Contributor
0 Kudos

Hi Hamayet,

It will be good, if you can share the resolution.

Regards

Terence

former_member249141
Participant
0 Kudos

Hi Hamayet

  Can you share your steps to resolve issue

Thanks ,

Virendra

Former Member
0 Kudos

Please assign Settlement cost element to every leves WBS. Not assign upper level WBS to lower level WBS.

Thank you

Rasel

former_member249141
Participant
0 Kudos

Dear Hamayet,

  I am also facing with same issue .  I have a 3 level of WBS & I am tried to settle the 1st level WBS to cost center as all cost are roll up to first level , but it it gives error Maintain settlement rule of sender & if i assign settlement rule for lower level WBS &sender as upper level WBS then system is throwing error of Item 001 WBS element xxxxxxx Budget exceeded , message no. BP604. I think it may be roll up double cost to upper level WBS from lower level WBS.

     Now I don't understand that whether I am doing something wrong process or system error because I am doing this process first time . Please help anyone ASAP.

 

Thanks ,

Virendra

former_member249141
Participant
0 Kudos

Hi Experts ,

  Please need help  to resolve this issue till I am stuck for the same .

@ Hamayet - Are your Issue resolve ??

Thanks ,

Virendra

Former Member
0 Kudos

Mr. Virendra

Can you please share the Message what you get?

Even you can go-through on this link 

It might be helping you.

If it is not work, then please share your faced massage screen shot.

Thanks.

Hamayet Rasel

former_member249141
Participant
0 Kudos

Dear Hamayet ,

Thanks for your reply , here I am sharing Screen shot of Error message please go through it also as mentioned above I have 3 levels of WBS & I have to settle the cost to Cost center (Either Project definition or first level WBS) . Also let me know your settlement steps.

Thanks ,

Virendra

MTerence
Active Contributor
0 Kudos

Hi Virendra,

In standard, system should not give a message like that at settlement, so refer this note, if you didn't come across the two solution mentioned in the note, then you need to raise to SAP.

Refer below note

1935079 - Error message BP604 budget exceeded during settlement


Regards

Terence