Hi guys
what are some of the MRP relevant fields that can trigger NETCH if they are changed?
Thank you
Hello Youssef,
Changes to stock, if these change the stock/requirements situation of the material
Creation of purchase requisitions, purchase orders, planned orders, sales requirements, forecast requirements, dependent requirements or reservations
Changing to fields that are relevant to the planning run for these receipts and issues or in the material master
Deleting receipt or issue quantities
Create an entry in the planning file
Also changes in
MARC-DISMM-MRP Type
MARC-PLIFZ-Planned Delevery Time
MARC-DISLS-GR Processing Time
MARC-SOBSL-Sp.Procurement Key
MARC-MINBE-Re-order point
Please refer,
Planning Run Type - Consumption-Based Planning (MM-CBP) - SAP Library
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks very much much appreciated
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Look into this blog post How to close a discussion and why | SCN
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.