Hi Guys,

Could you please let me know what is the difference between assigned budget ( value type 42 ) from BPJA & assigned budget value in SLR58 report.

Regards

Gaurav Ahuja

Accepted Solutions (0)

Answers (4)

Answers (4)

former_member210342
Participant
0 Kudos

Hi Gaurav,

Let me try to put some light on this..

S_alr_87013558 Report:-

As told by others...Assigned value is equals to Actual +commitment + Remordplan..

But this report reflect the values that are present in Tables and it can be different as table values(normally does not happen)

But when and how it happens :-

Tables are updating on the basis of project cost (any cost ) and availiabilty controls setting.

So whatever values are visible availiabilty control report( not SLR558 report) will be same as values in table.

Now where is this AVAC report,. you can find it CJ32 menu bar .. I think 2nd last one sub menu (written as availiabilty control).

This report will be same as tables values. Alr report should match with this report.( sometime it does not happen due to wrong setting of alr report or lack of notes)

This is difference in alr Report and assigned budget (It can be only the case..) . If u have some other issue then share screen shot..

I hope it wil help

Thanks

Rahul

sunil_yadav2
Active Contributor
0 Kudos

Hi Gaurav,

Assigned value in SLR report is addition of Actual, Commitment and RemOrdPlan.

Assigned Budget only shows up in either BPGE or BPJA based on the availability control, but not both.

thanks

Sunil

praveen_vanm
Participant
0 Kudos

Hi Gaurav,

In s_alr_87013558 report assigned budget is 

Actual + commitment = Assigned

I hope this will be help full

Regards

Praveen

Former Member
0 Kudos

Hi,

As per report s_alr_87013558

Assigned=Actual Cost+Commitment+RemOrdPlan

Regards,

Rao

sunil_yadav2
Active Contributor
0 Kudos

Hi Gaurav,

Please check below links:

http://scn.sap.com/thread/2083081

http://scn.sap.com/thread/3436895

try to run correction programs RKANBU01, RKACOR04 and CJEN.

hope this will help.

thanks

Sunil