Hi,

We need to maintain in house production time in MRP2 View in terms of Hours instead of Days.

Kindly suggest if any possibility for the same.

Thanks in advance.

Sudeep Jain

Accepted Solutions (0)

Answers (1)

Answers (1)

RahulHanda
Active Contributor
0 Kudos

Hi Sudeep,

The purpose of this is to do basic scheduling when MRP is executed. On the other hand is you want to do lead time time scheduling then maintain routing accordingly and select 2 (Lead Time Scheduling and Capacity Planning) while doing MRP run.

To get more on this refer SAP note

152319 - Consulting: Scheduling of planned order for routing


Let us know if it resolved your issue.


Regards

Rahul