Dear PS experts.
My client has a partial confirmation on a network activity. When they add another partial confirmation using CN25 to the same activity the defaulted work center and activity type are not the same as maintained currently in the network. Is it standard behavior for the confirmation to default the activity type and work center from previous confirmation(s) and not the current work center and activity type on the network? If so, is there a configuration setting that would allow the network confirmation to read the current activity type and work center on the network activity and not fetch these values from previous confirmation record?
My thanks to all. Toliver in Atlanta - GA
Hi Toliver,
Related to your issue, there was a similar case in SAP PM, refer below note.
1924019 - PM/CS confirmation : Default work Center and Activity Type is not set
SAP has given an option to change the enhancement CONFPM01. So i guess you can raise with SAP. Additionally i could not get a relevant note in SAP PS.
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Toliver,
Oddly, my business users have recently noticed this and asked me about it. I have looked about and have not found any definitive information confirming that this is by design. I have also not been able to find any settings that would do as you wish (my business users would also like this).
For now, let's see if anyone else can provide any insight into this.
Cheers,
Tony in Ottawa, Canada
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.