on 06-03-2015 11:47 AM
Hi,
I have assigned budget for 2014 only for single wbs element rs.1000 , then i have created PO qty 10 rs.50 for 2014 Doc.date and delivery date is 2014.
i havn't assign budget in 2015 then i posted GRN in 2015 aganist PO but it allowing to post actual cost.
where we can control for this in standard.
is there any scenario.
regards,
siddu
Dear,
Yes, system is checking the budget availability for the superior WBS element.For your requirement you can try with "Release budget" functionality.But at this moment it can not be done to this project.
Reagards,
Pardhu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
What about your P.Os delivery dates for this WBS element.
Kindly check the SAP Note: 444215 - Delivery date and commitment
Regards,
pardhu
Can you please try by allocating 1 INR/USD only against the subject WBS for Fy 2015 and try MIGO again and let us know if system gives budget error.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
Did you carry far worded the budget and commitments of this WBS element to 2015?
Regards,
Pardhu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.