on 06-03-2015 10:37 AM
Dear Guru,
I have a SNP PDS which has 3 operations, each one will have a different resources, which resource should be displayed in the SNP planned order? The 1st or 3rd, or there are some settings I can do to change it?
Please kindly help!
BR,
Lawrence
Hi Yang,
It will take the third, as this would be giving final output for this product. In RRP3 you would see the 3rd one.
Regards
Rahul