Resource displayed in SNP Planned Order

Dear Guru,

I have a SNP PDS which has 3 operations, each one will have a different resources, which resource should be displayed in the SNP planned order? The 1st or 3rd, or there are some settings I can do to change it?

Please kindly help!

BR,

Lawrence

Tags:
Former Member
replied

Hi Yang,

Logically that should not be the case. In PPDS plan order also it should show you last one. Cross check do you have only one resource in routing.

Regards

Rahul

0 View this answer in context