Without source of supply (PDS/PPM) planned order

Former Member
0 Kudos

Hi

Please let me know is it possible to find without source of supply  (PDS/PPM) planned order in APO?

Or any report available to find out the such inconsistency? Please guide.

Rgds

Surendra

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

HI SDB

You can check through /sapapo/rrp3 by giving necessary inputs

planning version

product

location

where yo can see all planned orders and there linking with sales orders

If you want to see in Mass go to /sapapo/rrp4 .

Regards

Virender

Former Member
0 Kudos

Thanks both of you. But in tcode /sapapo/rrp4 , resource and SOS filed is not available

My requirement is to see the SOS or resource along with planned order and material/plant.

or let me know any is any table available in APO.

RahulHanda
Active Contributor
0 Kudos

Hi,

Did you try RRP3, there resource is very much clear.

Regards

Rahul

Former Member
0 Kudos

RRP3 shown single product wise I want to check it collectively

RahulHanda
Active Contributor
0 Kudos

Hi,

Check /SAPAPO/CDPS_REPT. Select WIP list, put one or multiple location(s). This will show you both planned orders and production orders (which you can filter on the basis of number range and save as layout). This will show you materials and linked PPM/PDS.

Regards

Rahul

Former Member
0 Kudos

Hi SDB

Go to /sapapo/rrp4 and just find out your planned order and expand the planned order yo can see resource and availabilty date etc

AS per Rahul you can also check in CDPS_REPT

Regards

Virender

Former Member
0 Kudos

Thanks all .

RahulHanda
Active Contributor
0 Kudos

Could you close the thread accordingly so it's clear.

Regards

Rahul

Answers (4)

Answers (4)

Former Member
0 Kudos

I would like to add to the discussion only by sharing that we have a custom report prepared for the same since the output of the report really helps resolve errors. So you can discuss with a developer about the same. The batch job in our case is scheduled to run daily.

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

You can get it in /SAPAPO/PPL1 - Production List  and /SAPAPO/RRP4 - Receipts View set the layout accordingly.

Best Regards,

R.Brahmankar

Former Member
0 Kudos

Hi SDB,

Check in RRP4 in change layout if option Resource exist. If no, you can add a new column if you use BAdI /SAPAPO/RRP_IO_COL.

https://scn.sap.com/thread/3517385

Thanks,

Regards, Marius

RahulHanda
Active Contributor
0 Kudos

Hi,

Use /n/SAPAPO/RRP4 to see your receipts. Put the version 000, date range, product and on other tab put 1F-In-House Production in order type. This will give you planned orders for the same.

You could also use /n/SAPAPO/RRP3.

If you are talking about inconsistency do CCR (/n/SAPAPO/CCR) between the systems for this material. It would give you planned order number.

Let us know if it resolved your issue.

Regards

Rahul