on 06-01-2015 9:30 PM
Hi,
I am trying to model the scenario where I have a Finished good routing. One of its operations has a work center constrained by the equipment used in the work center. This operation is an inspection and uses a standard prototype to carry out the task. Each product has a unique prototype and there is only 1 prototype per product to verify against. How can I model this in routing since its a constraint on the resource but not a constraint to produce Finished good. The operation takes 10 min per 1 Unit/EA of product.
I am using APO to generate plans and the reason I need to consider this as a constraint is for a fact that I can generate plans for other products for max. resource utilization. Appreciate your inputs.
Regards
AK
Don't you think this should be a part of part of QM ?
Its not a bottleneck for production but for Inspection so ideally this can't be a part of routing which only pertains to production.
Still, If you want to map it. I suggest to have this Inspection Equipment as a separate Resource having the available capacity out of which 10 min can be used in routing of item like any regular WC/routing.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.