work center capacity levelling

I have un set of material, with a very simple production, one operation, one route. Imagine this situation. Material M1 , could be produced in the work center C1 or alternative in the work C2: the are two different work center, but they can produce M1 in the same way. Material M2 could be produced in work center C1 and C3 Material M3 could be produced in work center C3. Imagine that C1 is loaded at 130% and C2 is load only ad 30%., C3 is loaded at 40%. How can I setup materials, work center, routing in order to obtain an automatic leveling between work centers.. I mean, I would like that sap automatically recognize that C1 is loaded at 130% and switch part ofM1 production to C2or switch part of M2 production to C3. Keep in mind that the production process is very simple, one operation, one route. Thank you very much.

Former Member
replied

Hi Silvana

I suggest you to create two different production versions, one for each work center.

After that, on the strategy profile used for capacity leveling, you should select the option "Change production version on error". That way, system will dispatch the orders for the first work center, until finding an overload. When it finds an overload, an error is triggered and system tries to change the production version and dispatch to another work center.

BR
Caetano

0 View this answer in context

Helpful Answer

by
Not what you were looking for? View more on this topic or Ask a question