EHP 7 upgrade ACT_UPG in pre-processing running slow

Hi All,

We are upgrading our ECC system from EHP6 to EHP7. The pre-processing ACT_UPG phase is running for 18 hours. I have gone through all notes and set required things. I can see the job RDDMASGL is active in shadow system. there is no update in log folder. But i can see in tmp folder regular update is there SAPA742EPU.SID.I can see 1 EDO533X*** Activate objects at level "57" is completed. How many level will be there for active objects. Kindly help me on this.

Regards,

Karthik.R

Tags:
Former Member
Former Member replied


Hi Karthik,

Check the KBA : 1918279 - performance analysis for ACT_UPG phase

Best Regards,
Gaurav