Capacity levelling on transport resource

Dear all,

we are working on process to use the transport resource to model vendor capacity. Setup all required data

- created transport resource of type T, maintained weekly quantity capacity

- assigned transport resource to transport lane of vendor to plant

- maintained the consumption details on each product specific transport lane

- ran the supply heuristic on plant,

- purchase requs generated from vendor to plant

- purchase requisition shows capacity consumed on capacity book

But issue here is

- capacity levelling  is not not working

we tried both optimizer and heuristic capacity levelling, none of method levels the capacity

any idea, suggestion where we have to check so that process run.

Thank you in advance

With regards

Vijay

Former Member
Former Member replied

Hi Vijay,

Check at transport resource if the option Finite Scheduling is chosen! 

Thanks,

Regards, Marius