on 05-27-2015 8:23 PM
Hello,
We are planning to upgrade our dev systems from BI 4.1 Sp3 to BI 4.1 Sp5. As we have lot of developments going on in dev system with tight schedule, can we promote the contents ( reports) on BI 4.1 Sp 5 dev systems to BI 4.1 SP3 Quality and prod systems ?
Upgrading Q and P systems to Sp 5 may take a while ,I am checking the possibility promiting the contents without impact between SP5 and SP3 systems.
Thanks in advance for your advise !
Raj,
You would use the higher version to pull. You can only promote from lower to higher, never higher to lower.
Configurer Promotion Manager on BI 4.1 w/ SP5 to pull objects from BI 4.1 w/ SP3.
Regards,
Ajay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Always from lower to higher versions. You might see some issues if you do it with your approach.
But this practice is not recommended.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.