In our business we recived a material and was tested using qe51N and released with QA11.so now that the subsequent deliveries
from vendor should not go in to quality and directly it should go in to unrestricted.
I see that in Material master QM view, Inspection setup that
post to inspection stock is unchecked and still the stocks are posted to quality.
Dear experts what settings need to be changed to post stocks directly to unrestricted
I think people have lost sight of the original business requirement.
Is the requirement simply to manually turn off quality inspection for one material? Becasue that is what most of the previous respondents are describing here.
Or is the requirement to have a business process whereby new materials are routinely setup so that the first receipt of the material is inspected, and all future receipts go to unrestricted inventory. And is there any yearly reinspection required?
Maybe Yadagiri can clarify this a bit more?
Craig
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Yadagiri,
Summarizing the requirement as below(as per my understanding):
When received from Vendor for a particular material,Stock should directly go to unrestricted use instead of Quality Inspection Stock
But the above requirement raises below open questions:
1.Does the Inspection lot need to be created for this scenario for this particular material?
If the answer is yes,then activate 01 in the material master and un-check the "post to Inspection Stock" Indicator in the Inspection Setup for 01 Inspection Type as shown below.Hence the Stock will posted to Unrestricted use when doing GR
If the answer is "No" i.e., there is no need of an Inspection lot to be created,then deactivate the Inspection Type 01 in the Material Master
2.Does this requirement particular for a particular Material and Vendor?
If Yes,then using of Dynamic Modification Rule with Skip will work for this.
3.If the Requirement is irrelevant of the Material(Inspection Type) and vendor, i.e., no need of Inspection Lots created for the Goods Receipt from Vendor ,then check the "QM Not active" for the movement Type 101 and with Movement Indicator "B-Purchase Order" in SPRO path Quality Management->Quality Inspection->Inspection Lot Creation->Inspection for Goods Movements->Deactivate Quality Inspection for a Movement Type
Please let me know if this answered your question
Regards
Mohan
Hi,
I agree with Craig.
This is my assumption from his req:
First time vendor-material needs quality Inspection just to verify the incoming quality after this no further inspection is required.
proposed solution: You may need to use dynamic modification rule and Skip
1. QM View Inspection type settings ---tick Skips allowed
2. Created DMR (at lot creation) ---- Stage 1 ---Normal Inspection ---(Initial)
If OK-1- Stage 2 ; If Rejected-1-stage1
Stage2---Reduced inspection ---(Skip)
OK: No of Inspections-10, Max skip duration: 30 days, new insp stage-2
NOT OK: Rejections: 1, New Insp stage: 1
3. Create Inspection plan (Inspection lot level) and assign DMR in header and provide vendor material
4. system creates Inspection lot as normal for the first time and then after that further lots status will be SKIP and stock will be directly going to unrestricted.
5. You can use QA16 to do UD for Skip lots collectively or u can set background job.
experts pls correct me If I am wrong.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Yadagiri,
You can deactivate the inspection type from material master, if you do not want the GR inspection (Deactivate 01 inspection type). Otherwise, change the po order settings as suggested by gopinath.
Thanks
Prem
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
To make the quantity to go directly to unrestricted, all you need to do is set the indicator off for 'Post to insp stock' for the relevant inspection type. Seems you have already done that but still you get the quantity into QI.
Please share the inspection set up screen. Do you have any other inspection type active for the same material? I doubt you might haven't checked the indicator for the inspection type 01 but for some other.
Apart from that,
There are different settings for that and that's an different analogy.
ntn
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Yadagiri,
You should check your default settings in the MIGO screen if you have changed the stock type in material master. Probably you initially created the PO but later deactivated the inspection type. This would make the default stock type as quality stock when you do the good receipt.
Venkatesh and Nitin has suggested you correctly and you need to look after both the aspects. If 'post to inspection' tab is unchecked, you should check the stock type in MIGO screen as additional check.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Yadagiri,
Based on material master --> Quality management settings system will post the stock directly to unrestricted stock i.e. QM Procurement, Control key, Certification,Inspection types from inspection set up all these fields should be removed from material master
please try with the above settings and update the status
Regards,
Venkatesh..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Chandrasekaran,
we have maintained the following parameters in the material master
we have unchecked the QM Procurement key active and not maintained QM Control Key,Certificate type and inspection type in inspection setup is checked to 1 and post to inspection stock is unchecked.
can you please suggest me that unchecking the inspection type in inspection setup will solve my issue or any thing to be changed.
Dear Venkatesh,
we have maintained the following parameters in the material master
we have unchecked the QM Procurement key active and not maintained QM Control Key,Certificate type and inspection type in inspection setup is checked to 1 and post to inspection stock is unchecked.
can you please suggest me that unchecking the inspection type in inspection setup will solve my issue or any thing to be changed.
Dear Yadagiri,
Please delete that inspection type 01 from the inspection setup
sure system will post the stock directly to unrestricted only
after making the master data change then create the PO
select the inspection type and click on delete
Quality management view should be like this
after maintain these settings create a PO then do the GRN stock will directly posted to unrestricted only
if the PO already created means you can be able to change the quality to unrestricted in the MIGO screen
Regards,
Venkatesh..