【workload Distribution Per Hour】In one day,which program spend which resources

Former Member
0 Kudos

Hi SAP Experts,

To check the performance of our system, I want to know which program spend which resources in one day. For example, at 01:35 every day, the CPU idle is almost 100%, but at 9:00, the CPU idle is almost 0%, So I want to check the workload distribution per hour to assign hardware resources better.

In ST03N, I only find the average workload per day/week/month, there is no detailed information per hour. So How can check the workload distribution per hour?

Thanks

Best Regards

Shuai.zhongwei

Accepted Solutions (1)

Accepted Solutions (1)

former_member184455
Active Participant
0 Kudos

Hello Zhongwei,

In ST03 you'll find on the left side different 'Analysis Views'. Chose Time Profile and then double-click on the time interval you are interested in. In a Popup the transactions of this time interval will be presented.

Best Regards, Randolf