Target cost of Activity not updated during Costing RUN

Dear Exparts

We have observed that target cost of activity is not updating during costing run.

in routing display

in production order display


Tarek H Chy



What I could understand that In prod order your target cost is not updated properly because your standard cost is missing activity cost during costing run...please check the following areas:

  1. Activity type is properly created in KL01/02

  2. Planning is done in KP06/26 for activity dependent planning

  3. Price is calculated in KSPI and updated in KP26...see in KSBT

  4. Routing is properly defined with CCtr & Activity combination with proper formulas assignment

If all these ares are correct then you should get Activity cost in costing run...and also target cost in Prod Order