on 05-26-2015 10:24 AM
Hi
What I could understand that In prod order your target cost is not updated properly because your standard cost is missing activity cost during costing run...please check the following areas:
1. Activity type is properly created in KL01/02
2. Planning is done in KP06/26 for activity dependent planning
3. Price is calculated in KSPI and updated in KP26...see in KSBT
4. Routing is properly defined with CCtr & Activity combination with proper formulas assignment
If all these ares are correct then you should get Activity cost in costing run...and also target cost in Prod Order
kamal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
Check whether the Production version used for standard cost estimate is having these activities in the routing. If so check the costing lot size again the production batch size mentioned in the routing.
I see that 1 hr required for 10,000 PCS where as we are creating the Production order only for 100 PCS. ensure that the activity price and cost is good enough and not less than 0.00
Regards
Giri
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Tarek,
It will update once you run variance calculation for the order. So first do variance calculation, later check it.
Regards,
Mukthar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mukthar
During costing run product cost will update with RAW material and also Plan activity (Labour/Utiltiy etc)
In our case - plan activity rate not picking during costing run.
So that standard cost is picking only RAW material price.
And showing STD price BDT 29,700/-
After production we have discovered this issue.
Regards
Tarek H Chy