on 05-26-2015 4:57 AM
Hello Gurus,
I have weird situation happening in SAP. I have an inbound delivery with 2 items. I am performing GR via MIGO. I first GR one of the item. Afterwards, GR the other item. So I have 2 GR document in my inbound delivery. Here comes my issue, all items are GR however the status of my inbound delivery is still B. When I checked the GR documents, both of them have the same creation time. What might have caused this issue?
Regards,
Tomasz
Dear,
Can you share screens pls.
Regards,
Pardhu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Tomasz,
Check the below Note as well.Its will give some more idea regarding your issue
199703 - Goods receipt for inbound delivery using MB0A, MIGO, VL32
Regards
Logan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Tomasz,
In the SAP standard system you can only perform goods receipts using inventory management
transactions or post them using inbound deliveries.
Check the 570991 - Correction report for completing open inbound deliveries
Import the correction report Z_COMPLETE_INBOUND_DELIVERY and execute this report for those effected inbound deliveries.
Regards
Logan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.