on 05-22-2015 11:34 PM
Hi,
I am hoping someone has come across this issue. We are implementing a subcontracting scenario with Variant Configuration (VC). I have already done the costing configuration in COPC and my sales order are calculating costs and I can see condition EK02 with the correct cost (component + service coming from PIR).
When we create the purchase requisition and then purchase order I see the line for the service but when we run MIGO the system does the following posting:
Subcontracting Charges A/c Dr 1000.00
GR/IR Clearing A/c Cr 1000.00
Component Consumption A/c Dr 4000.00
Component Stock A/c Cr 4000.00
What I am expecting to see as well is the finish product coming into inventory and the following posting:
Assembly Stock A/c Dr 5000.00
Change in Stock A/c Cr 5000.00
Subcontracting Charges A/c Dr 1000.00
GR/IR Clearing A/c Cr 1000.00
Component Consumption A/c Dr 4000.00
Component Stock A/c Cr 4000.00
But because I do not have a standard cost in the material master we loose the cost. We currently have the subcontracting process set up for non VC part numbers and it works correctly and we have VC with production orders and it works with out issues.
Is there any configuration I need to do in COPC in order to calculate the cost in the PO and MIGO? like I mentioned before I can see my condition EK02 correctly in the sales order. Should the PO have a specific condition type that is relevant for VC that includes the component cost + service cost?
Thank you for your help!
Hello,
It's more like a logistic issue.
LO-VC.
BR,
Owen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.